Services: Civil | Categories: Site Work | Location: Long Island

Yaphank Correctional Facility

Location:
Yaphank, NY

Client:
Suffolk County DPW

Contract Value:
$13 Million

Project Dates:
2007 to 2008

Summary
  • Sanitary and Water Service Installations
  • Landfill Construction and Capping
  • Concrete and Block Retaining Walls and Vision Barriers
  • Asphalt Paving
  • Site Drainage and Sewer Contracting

PROJECT OVERVIEW

<iframe src=”https://player.vimeo.com/video/54419871?h=13b3d5a474&title=0&byline=0&portrait=0″ width=”640″ height=”360″ frameborder=”0″ allow=”autoplay; fullscreen; picture-in-picture” allowfullscreen></iframe>
<p><a href=”https://vimeo.com/54419871″>Yaphank Time Lapse</a> from <a href=”https://vimeo.com/posillico”>Posillico, Inc.</a> on <a href=”https://vimeo.com”>Vimeo</a>.</p>

The Yaphank Correctional Facility project originated as a 360 unit precast prison assembly. This project quickly changed to include the clearing and preparation of 35 acres for site staging of a precast concrete production and storage yard.

WHAT MADE THIS JOB COMPLEX

Because of the executive order mandating immediate construction, procurement for this project was greatly expedited. Therefore, the project had not been completely engineered and designed. Concrete precasting, usually done in an indoor controlled environment, had to be done on the site. Due to a short construction season, we had to mobilize very rapidly and expedite a detailed analysis of required resources and a quality control plan. This was the only way to ensure perfect production of precast materials under these uncontrolled conditions.

HOW POSILLICO SOLVED IT

Posillico set up three main production areas, one for each phase of precasting: 1) the fabrication preparation area 2) the forming and pouring area; and 3) the finish and staging area. Each area required a detailed pre-planned layout that anticipated each of the complex requirements of each phase. Just before the clearing and preparation of these areas, Posillico began mass excavation of the building site pad. This area consisted of thousands of yards of unsuitable fill that needed to be removed to eliminate excessive concrete foundations. During this time we focused on training and implementing an aggressive project control methodology, which focused on workers safety, Posillico was able to complete the precasting process and site construction ahead of schedule.