Town of Huntington Road Resurfacing

Location:
Huntington, NY

Client:
Town of Huntington

Contract Value:
$7.5 Million

Project Dates:
2012 to 2014

Summary
  • Curb and Sidewalk
  • General Road and Heavy Highway Construction
  • Site Drainage and Sewer Contracting
  • Asphalt Paving
  • Hot Mix Asphalt

PROJECT OVERVIEW

This resurfacing project entails the milling of damaged and deteriorated roadways and the installation of new asphalt throughout the Town of Huntington.

WHAT MADE THIS JOB COMPLEX

Working in such close proximity to homes and residents poses several obstacles. Safely directing vehicle and pedestrian traffic while adhering to the strict project timeline was key. Minimizing the impact on the daily lives of the town residents was very important to Posillico.

HOW POSILLICO SOLVED IT

The safety and well-being of workers and residents is always the most important aspect of a project. Posillico continues to work closely with the Town of Huntington to limit access to certain roads during construction. Local residents that must have access will be directed through the ongoing construction in a safe and organized manner.

Gallery