Kings Park Wastewater Treatment Plant

Location:
Kings Park, NY

Client:
Suffolk County DPW

Contract Value:
$11.5 Million

Project Dates:
2009 to 2011

Summary

Site Work, Building Work, & Plant Upgrades

PROJECT OVERVIEW

The project is the reconstruction of an existing wastewater treatment plant and the addition of a new 300,000 gallon per day Sequential Batch Reactor in Kings Park, New York. The contract consists of site work, building work, steel sheeting, tanks, electrical assistance, sewer piping and drainage work. It will also require concrete construction and rehabilitation of existing tanks.

WHAT MADE THIS JOB COMPLEX

Posillico is performing all of the work in and around this 70 year old active sewer plant that must maintain daily operations at all times.

HOW POSILLICO SOLVED IT

Posillico recommended several changes to the owner that has allowed us to complete the project on schedule. Changes included relocation and replacement of an existing 30 inch clay influent main to facilitate installation of new piping and value chambers. SCDPW and Posillico worked together to bypass 1/4 mile of the main and worked long days to minimize disruption to the plant.

Gallery