Kings Park Wastewater Treatment Plant
Location:
Kings Park, NY
Client:
Suffolk County DPW
Contract Value:
$11.5 Million
Project Dates:
2009 to 2011
Site Work, Building Work, & Plant Upgrades
PROJECT OVERVIEW
WHAT MADE THIS JOB COMPLEX
HOW POSILLICO SOLVED IT
Posillico recommended several changes to the owner that has allowed us to complete the project on schedule. Changes included relocation and replacement of an existing 30 inch clay influent main to facilitate installation of new piping and value chambers. SCDPW and Posillico worked together to bypass 1/4 mile of the main and worked long days to minimize disruption to the plant.