14th Street Ball Field Restoration

Location:
New York, NY

Client:
Con Edison

Contract Value:
$2.9 Million

Project Dates:
2013 to 2014

Summary
  • Thorough on-site Sampling; Testing and Analysis of Soils
  • Stone, Sand, Clean Fill
  • Transportation and Disposal of Contaminated Soils
  • Remediation
  • Site Drainage and Sewer Contracting

PROJECT OVERVIEW

Removal of existing sod field including impacted soils above NY state soil standards. Installation of drainage system, concrete footings and pads, site grading, installation of ball field structures (dugouts, backstops, benches, foul poles) and installation of a synthetic turf field.

WHAT MADE THIS JOB COMPLEX

Project was in the middle of Con Edison’s 14th Street Generating Station with many onlookers. There was tremendous pressure from Con Edison and the Little League to finish the project on time despite delays caused by factors out of Posillico’s control.

HOW POSILLICO SOLVED IT

Once issues were resolved, staff worked extended hours and weekends to try to complete the project as close to the scheduled end date.